by Usman Alabi Below are the images of the ongoing second pedestrian bridge at Ojota. The above is the metal stair way of the bride on the verge of being affixed to the main bridge. This is the second...
by Ajadi Daniel To these communities where the projects are abandoned, development is everything but a blessing. They are calling on the government to pull down the structures because they are now threat to lives and properties, according to the...
by Opeoluwa Quadri The light rail project was initially due for completion in 2011, The project however suffered delay due to funds. The project has been postponed on several occasions. Lagos light rail project is reputed to cost the state...
by YWriter The recent demolition of buildings at the Iwaya area of Lagos has drawn the attention of many. The demolition took place last week Friday, 18th August, 2017. There had been conflicting reports as to the exact reasons why...
by Chinedu Brown The ongoing construction of Pen Cinema flyover will be completed in the next 10 months, this is according to the Lagos state, Akinwunmi Ambode while on inspection of the site. “So, I have decided to do the Pen...
by Opeoluwa Quadri Alagbole flyover was started seven years ago according to residents, the project like the other four similar projects was supposed to take 24 months to complete, but even now, it is yet to see the light of...
by Ajadi Daniel Residents of former President Goodluck Jonathan’s hometown, Otuoke in Ogbia Local Government Area of Bayelsa have appealed to the state government to repair the Otuoke-Onuebum road which has been in a deplorable condition. The residents made this appeal...
by Usman Alabi Danfo drivers have varying opinion about the proposed plan to ban the iconic yellow buses in Lagos, some of them believe they cannot stop the government but encouraged them to consider engaging them why others said it...
by Ajadi Daniel S/N Projects Revised estimates 2016 Actual 2016 Budget 2017 1 Construction of 500 Nos Residential Housing Scheme in Lokoja (BD) 0 0 200,000,000 2 Construction/Beautification of Lokoja Round about 150,000,000 0 150,000,000 3 Ongoing construction of Ankpa/Imane/Mabene/Okpo road (30km) 100,000,000 0 100,000,000 4 Construction of Ankpa/Ogodo/Akwu Acharane road 100,000,000 0 100,000,000 5 Construction of Otoikiti Ganaja By pass multi-Lane carriage way (BD) 1,000,000 0 500,000,000 6 Construction of...
by Ajadi Daniel The ongoing construction of multiple layby in Ketu started in June 2017 and it is expected to be completed in May 2017, (12 months). Fountain Construction Company is the contractor in charge of the project. The Lagos...