by Usman Alabi
S/N | Project Name | Local Government | Status |
1
|
Construction of Re-inforced
Concrete Dual Carriage Flyover at Abule-Egba Junction along Abeokuta Expressway |
Ifako-Ijaye LG | Ongoing, 68%complete |
2 | Rehabilitation of Strategic Arterial/Inner Roads in Epe Phase 1 | Epe LG | Ongoing, 63% complete |
3 | Upgrading/Rehabilitation of New Market/Camp Davis/Ishefun (Section 1) | Alimosho LG | Ongoing, 97% complete |
4 | Upgrading/Rehabilitation of Aiyetoro road (section 1) | Alimosho LG | Ongoing, 84% complete |
5 | Rehabilitation of Oba Adeyinka Oyekan Road(Formerly Second Avenue) Ikoyi | Eti-Osa LG | Ongoing, 30% complete |
6 | Construction of Elegbede Street | Alimosho LG | Ongoing, 70% complete |
7 | Construction of Balogun/ Alade/Sunny/Adebisi/Adebosi/Adeyanju network of Roads | Epe LG | Ongoing, 72% complete |
8 | Completion of Igbo-nla Model College(Phase 2) Erodo | Epe LG | Ongoing, 79% complete |
9 | Construction of Leadforte Gate Avenue/Portion of Hon. Idowu Eletu/Ajelogo Street, Awoyaya | Ibeju-Lekki LG | Ongoing, 70% complete |
10 | Construction of Access Roads (Okusanya Network of Roads) to the Dana Plane crash location (Phase II) | Ifako-Ijaye | Ongoing, 57% complete |
11 | Construction of Arowojobe link Bridge and approach road at Mende Maryland | Kosofe LG | Ongoing, 5% complete |
12 | Construction of Harvey/Access to Grammar School Yaba, | Lagos Mainland | Ongoing, 69% complete |
13 | Construction of Bankole/Shodimu Streets with Bridge | Shomolu LG | Ongoing, 67% complete |
14 | Construction of Bolaji Omupo Street | Shomolu LG | Ongoing, 45% complete |
15 | Reconstruction of Lagos-Badagry Dual Carriageway(Lot 1) | Ongoing, 88% complete | |
16 | Construction of Ijegun-Isheri Osun-Isolo (Jakande Estate) Road | Alimosho LG | Ongoing, 88% complete |
17 | Dualization of Improvement of Isheri Olofin-Iba-Ojo(LASU) Road (Phase II) | Alimosho LG | Ongoing, 85% complete |
18 | Reconstruction of Lagos-Badagry carriageway(Lot 2A) | Amuwo-Odofin/Ojo LGAs | Ongoing, 34.65% complete |
19 | Reconstruction of Lagos-Badagry carriageway (Lot 2A)- Segment 1 | Amuwo Odofin/Ojo LGAs | Ongoing, 95% complete |
20 | Reconstruction of Lagos-Badagry carriageway (Lot 2A)- Segment 2 | Amuwo Odofin/Ojo LGAs | Ongoing, 54% complete |
21 | Reconstruction of Mushin Isolo Road | Mushin LG | Ongoing, 92% complete |
22 | Reconstruction of Lagos-Badagry carriageway(Lot 2A)-Segment 3 | Amuwo Odofin/Ojo LGAs | Ongoing, 8% complete |
23 | Reconstruction of Gaskiya College Road/Sari-Iganmu Road | Apapa | Ongoing, 98% complete |
24 | Construction of Ajare Age- Ilaso Poka/Erekiti road with bridge | Badagry LG | Ongoing, 68% complete |
25 | Completion of Ariyo (Mile 10), Ira-Muwo Bridge-Phase 1 | Ojo LG | Ongoing, 56% complete |
26 | Construction of Ipaye-Mission Road | Ojo LG | Ongoing, 64% complete |
27 | Construction of Afromedia-Adaloko Road, Phase 1 | Ojo LG | Ongoing, 79% complete |
28 | Construction of 4-legged Pedestrian bridges at identified locations within Lagos Metropolis. Between Ifako-Ijaye and Alomosho LGAs | Ifako-Ijaye and Alomosho LGAs | Ongoing, 78% complete |
29 | Construction of reinforced concrete flyover at Ajah and replacement of the existing roundabout with a signalized Intersection and rehabilitation of freedom road to Admiralty, Lekki-Ikoyi Link Bridge Roundabout in Eti-Osa LG | Eti Osa LG | Ongoing, 56% complete |
30 | Construction of Second Pedestrian Bridge, Ojota | Kosofe LG | Ongoing, 855 complete |
31 | Construction of reinforced concrete foot bridge at Okunudun/Itogbesa & Erekun Communities | Ojo LGA | Ongoing, 8% complete |
32 | Construction of Olugborogan Road by Conservation Park, Off Lekki-Eti-Osa Expressway | Eti Osa LG | Ongoing, 40% complete |
33 | Construction of Anuoluwapo street, Ejigbo | Oshodi-Isolo LG | Ongoing, 45% complete |
34 | Completion of the construction of Access Road to Olusosun Dumpsite, Ojota | Ikeja LG | Ongoing, 91% complete |
35 | Construction of Johnson Umejei Close, Ajao Estate | Oshodi-Isolo | Ongoing, 62% complete |
36 | Reconstruction of Ozumba Mbadiwe, Bonny Camp, Victoria Island | Eti Osa | Ongoing, 98% complete |
37 | Construction of floating Jetty at Ibeshe | Ikorodu LGA | Ongoing, 82% complete |
38 | Construction of Jetty with Terminal Buildings at Badore and Ipakodo | Eti Osa and Ikorodu LGAs | 100% complete at Ipakodo and 75% at Badore |
39 | Construction of Jetty with Terminal Buildings at Osborne Foreshore, Ikoyi. | Eti Osa LG | Ongoing, 79% complete |