Lagos tracker: Have you seen the list of ongoing projects in Lagos State?

by Usman Alabi

S/N Project Name Local Government Status
 

1

 

 

Construction of Re-inforced

Concrete Dual Carriage Flyover

at Abule-Egba Junction along

Abeokuta Expressway

Ifako-Ijaye LG Ongoing, 68%complete
2 Rehabilitation of Strategic Arterial/Inner Roads in Epe Phase 1 Epe LG Ongoing, 63% complete
3 Upgrading/Rehabilitation of New Market/Camp Davis/Ishefun (Section 1) Alimosho LG Ongoing, 97% complete
4 Upgrading/Rehabilitation of Aiyetoro road (section 1) Alimosho LG Ongoing, 84% complete
5 Rehabilitation of Oba Adeyinka Oyekan Road(Formerly Second Avenue) Ikoyi Eti-Osa LG Ongoing, 30% complete
6 Construction of Elegbede Street Alimosho LG Ongoing,  70% complete
7 Construction of Balogun/ Alade/Sunny/Adebisi/Adebosi/Adeyanju network of Roads Epe LG Ongoing, 72% complete
8 Completion of Igbo-nla Model College(Phase 2) Erodo Epe LG Ongoing, 79% complete
9 Construction of Leadforte Gate Avenue/Portion of Hon. Idowu Eletu/Ajelogo Street, Awoyaya Ibeju-Lekki LG Ongoing, 70% complete
10 Construction of Access Roads (Okusanya Network of Roads) to the Dana Plane crash location (Phase II) Ifako-Ijaye Ongoing, 57% complete
11 Construction of Arowojobe link Bridge and approach road at Mende Maryland Kosofe LG Ongoing, 5% complete
12 Construction of Harvey/Access to Grammar School Yaba, Lagos Mainland Ongoing, 69% complete
13 Construction of Bankole/Shodimu Streets with Bridge Shomolu LG Ongoing, 67% complete
14 Construction of Bolaji Omupo Street Shomolu LG Ongoing, 45% complete
15 Reconstruction of Lagos-Badagry Dual Carriageway(Lot 1)   Ongoing, 88% complete
16 Construction of Ijegun-Isheri Osun-Isolo (Jakande Estate) Road Alimosho LG Ongoing, 88% complete
17 Dualization of Improvement of Isheri Olofin-Iba-Ojo(LASU) Road (Phase II) Alimosho LG Ongoing, 85% complete
18 Reconstruction of Lagos-Badagry carriageway(Lot 2A) Amuwo-Odofin/Ojo LGAs Ongoing, 34.65% complete
19 Reconstruction of Lagos-Badagry carriageway (Lot 2A)- Segment 1 Amuwo Odofin/Ojo LGAs Ongoing, 95% complete
20 Reconstruction of Lagos-Badagry carriageway (Lot 2A)- Segment 2 Amuwo Odofin/Ojo LGAs Ongoing,  54% complete
21 Reconstruction of Mushin Isolo Road Mushin LG Ongoing, 92% complete
22 Reconstruction of Lagos-Badagry carriageway(Lot 2A)-Segment 3 Amuwo Odofin/Ojo LGAs Ongoing, 8% complete
23 Reconstruction of Gaskiya College Road/Sari-Iganmu Road Apapa Ongoing, 98% complete
24 Construction of Ajare Age- Ilaso Poka/Erekiti road with bridge Badagry LG Ongoing, 68% complete
25 Completion of Ariyo (Mile 10), Ira-Muwo Bridge-Phase 1 Ojo LG Ongoing, 56% complete
26 Construction of Ipaye-Mission Road Ojo LG Ongoing, 64% complete
27 Construction of Afromedia-Adaloko Road, Phase 1 Ojo LG Ongoing, 79% complete
28 Construction of 4-legged Pedestrian bridges at identified locations within Lagos Metropolis. Between Ifako-Ijaye and Alomosho LGAs Ifako-Ijaye and Alomosho LGAs Ongoing, 78% complete
29 Construction of reinforced concrete flyover at Ajah and replacement of the existing roundabout with a  signalized Intersection and rehabilitation of freedom road to Admiralty, Lekki-Ikoyi Link Bridge Roundabout in Eti-Osa LG Eti Osa LG Ongoing, 56% complete
30 Construction of Second Pedestrian Bridge, Ojota Kosofe LG Ongoing, 855 complete
31 Construction of reinforced concrete foot bridge at Okunudun/Itogbesa & Erekun Communities Ojo LGA Ongoing, 8% complete
32 Construction of Olugborogan Road by Conservation Park, Off Lekki-Eti-Osa Expressway Eti Osa LG Ongoing, 40% complete
33 Construction of Anuoluwapo street, Ejigbo Oshodi-Isolo LG Ongoing, 45% complete
34 Completion of the construction of Access Road to Olusosun Dumpsite, Ojota Ikeja LG Ongoing, 91% complete
35 Construction of Johnson Umejei Close, Ajao Estate Oshodi-Isolo Ongoing, 62% complete
36 Reconstruction of Ozumba Mbadiwe, Bonny Camp, Victoria Island Eti Osa Ongoing, 98% complete
37 Construction of floating Jetty at Ibeshe Ikorodu LGA Ongoing, 82% complete
38 Construction of Jetty with Terminal Buildings at Badore and Ipakodo Eti Osa and Ikorodu LGAs 100% complete at Ipakodo and 75% at Badore
39 Construction of Jetty with Terminal Buildings at Osborne Foreshore, Ikoyi. Eti Osa LG Ongoing, 79% complete

 