Agege flyover

24 February 2020

The Agege flyover project is still ongoing [Photos]

  Work is still ongoing on the Agege flyover project, the project is reaching its advanced stage. Hopefully, the project that is meant to be complemented […]
23 January 2020

Tracking the ongoing flyover over project in Agege, Lagos

  Agege flyover project was started by the last administration, was abandoned for a while before it was continued by the present administration. We report that […]
17 May 2019

Work still on hold at the site of Agege flyover project

by Ajadi Daniel The project was meant to be completed late last year, but currently the site has been deserted and. We report that work is […]
10 April 2019

Lagos tracker: Agege flyover project joins the list of abandoned projects in Lagos

by Ibrahim Faleye, The Agege flyover project is yet to be completed despite promises from the Lagos state government that the project would be completed November […]
8 February 2019

Agege flyover has exceeded the date of delivery by three months, yet the project is still ongoing

by Ajadi Daniel Agege flyover project is not new to the Lagos budget, it has been in the budget for almost two years before it was […]